- Reading down a column reveals which tasks receive information from the task corresponding to the column.
- The diagonal cells are usually filled in with dots or the task labels, simply to separate the upper and lower triangles of the matrix and to facilitate tracing dependencies.
- Gantt Chart :-> shows how the work is broken down into a set of activities
id:: 648afdb9-eed3-47a1-bdf7-42e83a0b1b40
- Features: #flashcard
id:: 648adeaf-7e45-4525-b935-ef9a0357b961
- They show the scheduling of these activities as a series of horizontal bands against a series of vertical lines representing dates
@ -1385,7 +1386,9 @@
- The Critical Path #flashcard
id:: 648adeaf-08be-4aa8-989a-f39a68c2e9a0
- The _dependencies_ :-> among the tasks in a PERT chart, some of which may be arranged sequentially and some of which may be arranged in parallel, lead to the concept of a critical path.
id:: 648afdb9-eeb6-4637-907f-c26da7231fd8
- The _critical path_ is :-> the longest chain of dependent events. This is the single sequence of tasks whose combined required times define the minimum possible completion time for the entire set of tasks.
id:: 648afdb9-a6bc-4521-99e2-a8a69f0c1f1f
- Undertake a baseline project plan
- **Definition** :-> project plan is the roadmap for the remaining development effort. The plan is important in coordinating the remaining tasks and in estimating the required development resources and development time.